Day-of Generator Install 12-Point Protocol
Our standard install day, step by step. Site prep through final sign-off — the routine our crew runs on every whole-home standby generator install in SE Michigan.
📞 (248) 266-5597Confirm setbacks, mark gas/electric lines, verify DTE coordination status.
Oakland/Macomb permit, generator spec sheet, plot plan, and gas meter upgrade paperwork reviewed before any digging.
Composite pad set per manufacturer template, level within 1/4", code-compliant from structure and property line.
Air-cooled unit or liquid-cooled set bolted to pad, vibration isolators per install guide.
Verify BTU load against meter capacity; CSST or black-iron per local code and DTE requirements.
Confirm meter upgrade is complete or scheduled; pressure-test gas line before energizing.
Feeder from transfer switch to generator, in conduit, sized per load calc.
ATS installed next to existing main panel, conductors landed, neutral and ground bonded per code.
Controller programming, exercise cycle set, mobile link / Wi-Fi paired if applicable.
Open mains, verify transfer within rated seconds, walk every circuit, confirm no nuisance trips.
Operation walkthrough, mobile app install, maintenance interval explained, emergency contact shared.
Township/county inspector walks the job; approval sticker filed; warranty paperwork and invoice delivered.